6 Months in 6 Minutes

Take a look at The Amelia Scott progress from January 2020 in this video; 6 months in 6 minutes!

So far, 202 tonnes, or 1 ¾ blue whales equivalent, of hardcore waste has been removed from the site, and 40 tonnes of rebar has been used, which is about as heavy as the space shuttle!  The team have been working hard on and off the construction site to achieve their milestones and despite the covid-19 challenges they are still on programme. The Amelia Scott redevelopment is now really starting to take shape. The construction work is continuing under social distance guidelines from central government.